Tbilisi Energy released information about the capital’s gas supply.
“Current data: Didube-Dighomi: 19,700 subscribers – fully connected; Vake-Tskneti: 43,900 – 55% connected – 19,755 connections are underway. Saburtalo Nutsubidze: 87,200 subscribers – 55% connected – 39,240 subscribers are being connected. The work continues intensively. The company is fully engaged. We aim to provide gas to all subscribers by 23:00,” the information says.
Due to damage to the central gas pipeline, the gas supply has been cut off for two days to about 150,000 subscribers in the Vake and Saburtalo districts of Tbilisi.
The 500 mm central gas pipeline was damaged under unknown circumstances, most likely by a third party, Tbilisi Energy said.
Related story: February 10: Tbilisi Energy: Gas supply restoration underway, full recovery expected by end of day on February 11